Klamath Falls Campus : Construction Schedule

Anticipated

Project Timeline

Project

Name

Project LocationAnticipated ImpactsOther/Notes

April 15, 2024-

August 29, 2025

New Student HousingArea between Arboretum and CU. (Tennis Court Area)Permanent closure/removal of the tennis courts

Early work:

4/15/2024-6/7/2024

Construction:

6/10/2024-8/29/2025

June 17, 2024-

August 30, 2024

Boivin Traffic ImprovementsIndustrial Park DriveLot E and Industrial Park Drive will be closed/inaccessible for duration of project.Deliveries via Campus Dr to East & North University Drive

May 20, 2024-

April 25, 2025

Geothermal Phase 1 Building RenovationSoutheast corner of campus. (Geothermal Heat Exchange Building)There will be planned geothermal shutdowns which could temporarily affect access to hot water. 

June 17, 2024-

August 30, 2024

Geothermal Phase 2 Distribution PipingCampus wide. Some access restrictions to Lot B.There will be planned geothermal shutdowns which could temporarily affect access to hot water. 

June 3, 2024-

December 27,

2024

ABA Clinic Renovation200 Commercial StreetNo impacts on Klamath Falls Campus 

*Athletics reroof may be added if funding is identified.

For more information, reach out to Facilities at 541-885-1690


 

Active Projects

  • Description: New 85,000 sf, four-story building with 511 beds.
  • Status: Site mass excavation is underway.
  • Start Date: April 15, 2024
  • End Date: August 29, 2025

 

  • Description: Industrial Park Drive improvements between Dan O’Brien and Facilities Loop Road
  • Status: Project notice to proceed June 17, 2024
  • Start Date: June 17, 2024 
  • End Date: August 30, 2024 

 

  • Description: Renovation of campus' main Heat Exchange building 
  • Status: Project currently bidding
  • Start Date: May 20, 2024
  • End Date: April 25, 2025 

 

  • Description: New geothermal distribution piping
  • Status: Project in design
  • Start Date: June 17, 2024
  • End Date: August 30, 2024

 

  • Description: Interior building renovation for ABA clinic
  • Status: Project currently bidding
  • Start Date: June 3, 2024
  • End Date: December 27, 2024

 

Description: New membrane roofing on Snell Hall and Athletics
Status: Project currently bidding.
Start Date: June 17, 2024
End Date: August 20, 2024 

Previous Projects

 


  • Scope: Renovation of 47,000 square foot education building
  • Funding: UPE 803 / XI-Q Bond
  • Status: Project Underway
  • Start Date: February 2022
  • Completion Date: June 2023

Concrete sit steps at Boivin-Semon courtyard
Metal Framing
Middle section interior demolition
Installing new MEP equipment
Interior West Side-Bovin
Metal Wall and Flashing

 

Scope: Renovation of Ë¿¹ÏÊÓƵ Tech track, field, and stadium facility
Funding: UPE 789 / UPE 807 Lottery
Status: Project Underway
Start Date: May 2021
Completion Date: February 2023

The track and field renovation is 100% complete and the stadium renovation is underway.


interior demolition
installation of new exterior
stadium painting
Track turn 4 demo
Finished turn four
New OT Track 2022

 

Scope: New 30,000 square foot facility
Funding:  UPE796 – UPE817 OMH403 – OMH404 / XI-Q Bonds and State Grants
Status: Project Underway
Start Date: July 2021
Completion Date: February 24, 2023​​​​​​​ 


additive innovation center
additive innovation center - exterior
additive innovation center 2

 

Scope: New roundabout at Campus Way-Dan O'Brien intersection
Funding: UPE 803 / XI-Q Bond
Status: Design 90% complete 
Start Date: June 2021
Completion Date: September 2021

Campus Way

Scope: Completion of two unfinished spaces in the lower level of DOW
Funding: Program funded / DPT001
Status: Design underway
Start Date: June 2021
Completion Date: Awaiting to be determined 

DOW Physical Therapy Department

Scope: Addition to existing building
Funding: Department funded / SHS301 and SHS601
Status: Design 70% complete
Start Date: June 2021
Completion Date: December 2021

ISHC

Scope: Renovation of OT track facility
Funding: Will provide when available
Status: Design completed
Start Date: May 2021
Completion Date: September 2021

Stadium

Scope: Partial exterior renovation of existing building
Funding: UPE 797 / Capital Improvement and Renovation (CIR)
Status: Design underway
Start Date: June 2021
Completion Date: September 2021

Snell Hall exterior renovation